GEORGIA CONSTRUCTION LAW
TABLE OF CONTENTS................................................................i
PREFACE.........................................................................................
x
ACKNOWLEDGEMENTS..........................................................xiii
ABOUT THE AUTHORS............................................................
xv
CHAPTER ONE LICENSING..................................................
1
I.
INTRODUCTION....................................................................
1
II.
RESIDENT
CONTRACTORS................................................
3
A. What is
a resident
contractor?......................................................
3
B. Public
Works................................................................................
4
1. THE
STATE OF
GEORGIA................................................
...4
2.
GEORGIA DEPARTMENT OF TRANSPORTATION..............6
3. GEORGIA STATE FINANCING AND
INVESTMENT COMMISSION (GSFIC)
.7
4. CITY
OF
ATLANTA..................................................................
7
C.
RESIDENTIAL AND GENERAL CONTRACTORS................ 8
1. Licensing Requirements for
Residential-Basic and Residential-Light Commercial
Contractors
9
III.
SUBCONTRACTORS.............................................................15
1.
Electrical
Contractors...................................................................16
B. Master
and Journeyman
Plumbers................................................17
1.
Decisions.....................................................................................
18
C.
Conditioned Air
Contractors........................................................
19
D. Low
Voltage
Contractors.............................................................
20
E.
Utility
Contractors.......................................................................
21
IV.
EXEMPTIONS.......................................................................
22
A. Trade
Specialty/ Limited Service Specialty Contractors............
22
1.
Classroom
Trailers......................................................................
23
2.
Environmental
Remediation........................................................23
3.
Sitework..............................................................................
24
4.
Outdoor Environment
(pools)............................................. 24
5.
Streetscapes.........................................................................
25
6.
Concrete
Work....................................................................
25
7.
Masonry...............................................................................
26
8. Rough
Carpentry.................................................................
26
9. Finish
Carpentry..................................................................
27
10.
Remediation....................................................................
27
11.
Siding and Cornice
Work................................................ 27
12.
EIFS and
Stucco.............................................................
28
13.
Re-Roofing of Existing
Structures.................................. 28
14.
Drywall, Insulation, Studs &
Acoustical........................ 28
15.
Pre-manufactured Metal and Fabric Canopies................
29
16.
Refrigeration (not free
standing)..................................... 29
17.
Greenhouses....................................................................
29
18.
Pre-engineered Metal
Building....................................... 30
19.
Industrial Specialty
Work............................................... 30
20.
Boilers.............................................................................
31
21.
Cooling
Tower.................................................................
31
22.
Turf, Track and
Field......................................................
31
23.
Tennis
Court....................................................................
32
24.
Parks and
Recreation.......................................................
32
25.
Cell
Towers.....................................................................
33
26.
Sewage Pump
Station.....................................................
33
27.
Landfills..........................................................................
34
28.
Dams &
Reservoirs..........................................................
34
29.
Industrial Process Equipment and
Piping....................... 34
V.
RECIPROCITY...............................................................35
VI.
NONRESIDENT CONTRACTORS...............................35
A.
Nonresident Contractor
Act.................................................35
CHAPTER TWO BIDDING..............................................37
I.
INTRODUCTION...........................................................37
II.
PUBLIC
PROJECTS........................................................37
A. A.
Types of Delivery
Systems............................................. 37
1.
Design-Bid-Build................................................................
37
2.
Construction Manager/General
Contractor......................... 38
3.
Design-Build.......................................................................
38
B.
Competitive Bidding and Bid Solicitation
Issues.................39
C.
Procurement
Laws.................................................................39
1. Public Works Contracts by
State Departments, Boards, Bureaus, Commissions, Offices, or
Agencies Department of Administrative Services (O.C.G.A.
§§ 50-5-67 to 50-5-72)
..40
2. The
Bidding
Process...........................................................
42
3. Public Works Contracts by
the State Board of Education (O.C.G.A. §§
20-2-520)
45
4. Public Works Contracts by
Counties, Municipal Corporations and Other Government
Entities
45
5. Public Works Contracts by
the Georgia Department of Transportation (GDOT) (O.C.G.A. §§
32-2-60 to
32-2-74)...............................................................................
53
6. Bidding Law for Public
Works Contracts by the State Road and Tollway Authority
(O.C.G.A. §
32-10-68).......................................................................................
60
7. Bidding Law for Public
Works Contracts for County Road Systems (O.C.G.A. §§ 32-4-60
to
32-4-74)........................................................................................60
8. Public Works Contracts for
Municipal Road Systems (O.C.G.A. §§ 32-4-110 to
32-4-123)
63
III.
PRIVATE
PROJECTS...........................................................
66
IV. WITHDRAWAL,
MODIFICATION, RELEASE, AND EXPIRATION OF
BIDS
67
A.
Withdrawal of
Bids......................................................................67
1.
Generally......................................................................................67
2. Before
Formal
Acceptance..........................................................68
3. Consideration of Other Bids
After Withdrawal/Resubmitting Bids
..69
4.
Modification of
Bids...................................................................70
B.
Expiration of
Bids.......................................................................70
1.
Competitive Sealed
Bids............................................................70
2.
Competitive Sealed
Proposals....................................................71
C. Bid
Bonds
(Generally)................................................................71
D.
Equitable
Rescission...................................................................71
1. Bids
on Private
Projects..............................................................71
2. Equitable Rescission is
Unavailable as a Remedy for Bids on Public
Projects
..
.72
V. BID
PROTESTS....................................................................72
A.
Administrative
Remedies...........................................................73
B. Right
to Reject
Bids...................................................................74
C.
Standing to Bring a
Protest........................................................74
1. Low
Bidders..............................................................................74
2.
Rejected
Proposer.....................................................................
74
3.
Taxpayer
Standing.....................................................................75
D.
Available Due
Process.............................................................
75
1.
Hearing for Prospective
Bidders...............................................75
2.
Available
Relief.........................................................................75
CHAPTER THREE ARCHITECT
AND ENGINEER......77
I.
INTRODUCTION..................................................................
77
II. STATE REGULATION OF
ARCHITECTS AND ENGINEERS
78
A.
Architects.....................................................................................78
1.
Architect Licensure
Requirements..............................................78
B.
Engineers.....................................................................................82
1.
Engineer Licensure
Requirements..............................................82
III.
POTENTIAL LIABILITY FOR DESIGN PROFESSIONALS
..84
A. Sources
of
Liability.................................................................
85
1. Breach
of
Contract..............................................................
85
2.
Performance Deficiencies Which Lead to Claims...............
86
3.
Negligent
Design.................................................................
87
4.
Negligent
Supervision.........................................................
89
5. Liability to third parties
for duties created by law or accepted industry
standard 92
B.
Standard of Care
Affidavits...................................................
93
1.
Requirements.......................................................................
93
2.
Purpose................................................................................
93
3.
Application..........................................................................
94
4.
Failure to Follow
Statute.....................................................
94
IV.
CONTRACTUAL LIMITATIONS OF LIABILITY.......94
CHAPTER FOUR CONTRACTS.....................................97
I.
INTRODUCTION.............................................................97
II.
INTERPRETING CONTRACTS......................................
98
III.
IMPORTANT CONTRACT CLAUSES...........................100
A. Payment
Clauses...................................................................
100
B.
Indemnification
Clauses........................................................
104
C.
Termination
Clauses..............................................................
106
1.
Termination for
Convenience.................................................106
2.
Termination for
Cause............................................................107
D. Force
Majeure........................................................................
108
E.
Warranty of Plans and
Specifications................................... 110
1. The
Spearin
Doctrine..............................................................111
2. The
Builders
Warranty..........................................................112
3.
Express
Warranties.................................................................115
4.
Disclaimers............................................................................
116
F.
Provisions Relating to the Timing of
Performance............... 116
G. No
Damages for
Delay..........................................................
118
H.
Flowdown
Provisions............................................................
119
I.
Waiver of Jury
Trial...............................................................
120
IV. BREACH
OF CONTRACT ACTIONS................................. 121
A.
Substantial
Performance........................................................
122
B.
Attorneys'
Fees......................................................................
122
CHAPTER FIVE CHANGE
ORDERS AND EXTRA WORK.....
124
I.
INTRODUCTION................................................................
124
II.
WHAT IS EXTRA
WORK?................................................ 124
III.
CARDINAL
CHANGE.......................................................
127
IV.
DEDUCTIVE CHANGE ORDERS....................................
128
V.
RECOVERY IN QUANTUM MERUIT............................. 129
VI.
NOTICE AND PROCEDURE REQUIREMENTS............ 134
A. Does
the notice provision
apply?.......................................... 135
B. Was
notice
sufficient?...........................................................
136
C. Is
there actual
notice?............................................................
136
D. Did the owner waive the
notice or written change order requirement?.....137
E. Can an
oral change order be
enforced?................................. 138
CHAPTER SIX DIFFERING
SITE CONDITIONS.......140
I.
SHIFTING OF
RISK...........................................................
140
II.
DIFFERING SITE CONDITIONS CLAIMS TYPES....... 141
III.
DEFENSES..........................................................................
142
A.
Exculpatory
Clauses..............................................................
142
B. Notice
Requirements.............................................................
143
IV. CHANGED CONDITIONS
ABSENT CONTRACT CLAUSES 143
CHAPTER SEVEN DELAY
AND DISRUPTION............147
I.
INTRODUCTION................................................................
147
II.
DELAY.................................................................................
148
A. Time is
of the
Essence...........................................................
148
B.
Inexcusable, Excusable, and Compensable
Delay................ 149
C. Notice
Requirements Associated with Project Delay........... 152
D.
Concurrent
Delay..................................................................
154
E. No
Damages for
Delay..........................................................
154
F. Delay
Damages.....................................................................
156
1.
Liquidated
Damages.........................................................
156
2. Delay
Damages Available to the Contractor..................... 157
G.
Incorporation by
Reference...................................................
158
H.
Liquidating
Agreements........................................................
159
I.
Acceleration and Constructive
Acceleration......................... 160
III.
DISRUPTION......................................................................
161
CHAPTER EIGHT LIMITATIONS
OF ACTIONS..........165
I.
STATUTES OF
LIMITATION............................................ 165
A.
Contract
Actions...................................................................
165
B. Tort
Actions..........................................................................
167
1.
Actions for Injuries to
Persons.......................................... 167
2.
Actions for Damage to Real
Property............................... 168
II.
STATUTE OF
REPOSE.......................................................
169
CHAPTER NINE BONDS........................................................171
I.
INTRODUCTION................................................................
171
II.
PAYMENT
BONDS............................................................
172
A. Statute
Of
Limitations..........................................................
176
B.
Remedies...............................................................................
176
III.
PERFORMANCE
BONDS................................................. 177
A.
Remedies...............................................................................
178
CHAPTER TEN
LIENS...........................................................181
I.
HISTORY AND
PURPOSE................................................ 181
II.
ENTITLEMENT TO LIEN RIGHTS..................................
182
A.
Property/Property Interests Subject To
Liens....................... 184
III.
BURDEN OF PROOF/STANDARD OF REVIEW........... 185
IV.
BURDEN TO BRING SUIT/PRIVITY..............................
185
V.
BURDEN OF PROOF/USE OF MATERIALS.................. 185
VI.
BURDEN PAYMENT DISPUTE....................................
186
VII.
PROPERTY INTERESTS SUBJECT TO LIENS............... 186
VIII.
STATUTORY REQUIREMENTS......................................
187
A. Notice
of
Commencement....................................................
187
B. Notice
to
Contractor.............................................................
188
C.
Preliminary Notice of
Lien.................................................... 189
IX.
PERFECTING A CLAIM OF
LIEN................................... 189
X.
GEORGIAS NEWLY REVISED LIEN STATUTE......... 190
XI.
CONCLUSION....................................................................
192
CHAPTER ELEVEN LITIGATION
AND ALTERNATIVE DISPUTE RESOLUTION
..
193
I.
INTRODUCTION................................................................
193
II.
MEDIATION.......................................................................
194
III.
GEORGIA ARBITRATION CODE...................................
196
A. General
Statutory
Provision..................................................
196
B. The
Scope of
Arbitration.......................................................
196
1.
Specific Issues Reserved for
Arbitration.......................... 196
2.
Gateway/Threshold Issues for
Arbitrating........................ 197
3.
Enforcing an Arbitration
Provision................................... 199
4.
Discovery..........................................................................
202
5. The
Hearing.......................................................................
203
6.
Determination of an
Award.............................................. 204
7. Change
of an Award by the Arbitrators...........................
205
8. Courts Confirmation of an
Arbitration Award and Entry of Judgment 206
9.
Courts Vacatur of an Arbitration
Award......................... 207
10. A Courts Modification of an
Arbitration Award............. 210
IV.
FEDERAL ARBITRATION
ACT...................................... 211
A. General
Statutory
Provision..................................................
211
B.
Gateway/Threshold
Issues....................................................
211
1.
Arbitrability Involving Parties to a
Contract..................... 211
2.
Arbitrability Involving Nonsignatories to a Contract.......
213
3. Waiver
of Right to
Arbitrate............................................. 214
C. The
Scope of an Arbitration
Agreement............................... 214
1.
Transactions Involving
Commerce.................................... 214
D.
Enforceability of an Arbitration
Provision............................ 215
1. Based
on the
Agreement...................................................
215
2.
Restrictions on
Enforceability...........................................
215
E.
Enforcing an Arbitration
Provision....................................... 216
1.
Application for
Enforcement............................................ 216
2. Stay
of Pending
Litigation................................................
217
F.
Arbitration
Procedure............................................................
217
1.
Choosing an
Arbitrator......................................................
217
2. The
Hearing.......................................................................
217
G. A Courts Confirmation of an
Arbitration Award and Entry of Judgment 217
H. A
Courts Vacatur of an Arbitration
Award......................... 218
1. Notice
of Motion to Vacate an Award.............................
218
2. Cannot Serve as a
Collateral Attack on a Motion to Confirm an Award 219
3.
Grounds for Vacating an
Award...................................... 219
4.
Rehearing upon a Vacated
Award.................................... 220
5.
Appealing a District Courts Vacatur
Decision................. 220
I. A
Courts Modification/Correction of an Arbitration Award 221
J.
Appeals of District Court Arbitration
Decisions................... 222
1. Order to Compel Arbitration
is a Final Order Subject to Appeal 222
2. Stay
of Litigation Pending
Appeal................................... 223
3.
Standard of Review for Order to Compel Arbitration..... 223
V.
VERTICAL CHOICE OF LAW /PREEMPTION.............. 223
A. General
Principle...................................................................
223
B.
Enforceability of an Arbitration
Provision............................ 223
C. Choice
of Law
Provision.......................................................
224
D.
Confirming an
Award...........................................................
224
E.
Vacating an
Award...............................................................
225
F.
Insurance
Claims...................................................................
225
VI.
LITIGATION.......................................................................
225
A. As the
Result of No Valid Agreement to Arbitrate.............. 225
B. As the
Result of an Exception to the Georgia Arbitration Code
...... 225
C.
Insurance...............................................................................
226
D.
Residential Real
Estate.........................................................
226
1.
Initialing
Requirement...........................................................
226
2.
Inapplicable to Home Building
Agreements...................... 226
E.
Personal Injury Tort
Claims...................................................
226
TABLE OF LAWS AND
RULES.........................................227
TABLE OF CASES..................................................................
237
INDEX..........................................................................................252