CALIFORNIA

 

About the Author  |  This Book's Table of Contents  |  Order this Book  |  Seminars  |  Sponsors  |  Return to Map


CALIFORNIA CONSTRUCTION LAW
Table of Contents



PREFACE    xxvii

ABOUT THE EDITORS    xxix

CHAPTER ONE    1
CONTRACTOR LICENSING LAWS    1

I.    OVERVIEW OF CALIFORNIA’S CONTRACTOR’S LICENSE LAW    1
A.    Purpose of License Laws    2
B.    Applicability of License Laws    2
C.    Violations of License Laws    3

II.    WHEN A CONTRACTOR’S LICENSE IS AND IS NOT NEEDED    3
A.    When a Contractor’s License is Required    3
B.    When a Contractor’s License is Not Required    5
1.    Theoretical Exceptions to Contractor’s License
                           Requirement    5
2.    Statutory Exceptions to Contractor’s
                           License Requirement    6

III.    CONTRACTOR LICENSE CLASSIFICATIONS    7
A.    Class A - General Engineering Contractor    7
B.    Class B - General Building Contractor     8
C.    Class C - Specialty Contractors    9

IV.    ISSUANCE OF THE CONTRACTOR’S LICENSE    10
A.    Form of the Business    10
B.    Requirements for a Contractor’s License    11
C.    Reciprocity    11

V.    QUALIFYING PERSONS    12
A.    Individual    12
B.    Partnership    12
C.    Corporation    12
D.    Limited Liability Corporation    12
E.     Requirements for a Person Qualifying on Behalf
        of an Individual or Business Organization    12

VI.    VIOLATIONS OF CONTRACTOR’S LICENSE LAWS    14
A.    Acts Resulting in Automatic Suspension    14
1.    Disassociation of the RMO/RME/RMM     14
2.    Failure to Maintain Workers’ Compensation Insurance    15
3.    Failure to File or Maintain Required Bonds    16
4.    Failure to Pay Taxes    16
5.    Failure to Comply with Arbitration Award    16
6.    Failure to Pay Civil Penalty or Comply with
       Order of Correction or Citation    16
7.    Partnership Issues    17
8.    Corporation and LLC Issues    17
9.    Joint Venture Issues    17
B.     Acts Resulting in Disciplinary Actions    18
1.    Misrepresentations or Failure to Report
       Changes to the CSLB    18
2.    Abandonment of Contract    18
3.    Failure to Diligently Prosecute Work    18
4.    Diversion or Misapplication of Funds or
       Property    18
5.    Failure to Promptly Pay Subcontractors    19
6.    Disregard of Plans, Specification, or
       Accepted Trade Standards    19
7.    Violation of Statutes or Safety Provisions    19
8.    Failure to Keep Records for 5 Years    19
9.    Failure to Cooperate in CSLB’s Investigation of Complaint    20
10.    Failure to Complete Project for Contract Price    20
11.    Avoidance of Settlement Obligations    20
12.    Willful or Fraudulent Act    20
13.    Acting as Contractor While Improperly
Licensed    20
14.    Willful or Deliberate Failure to Pay for Material
         or Services    20

VII.    PENALTIES FOR VIOLATING CONTRACTOR’S LICENSE LAWS    21
A.    The “Shield”: Denial of Unlicensed Contractor’s Right to     Sue for Compensation    21
B.    The “Sword”: Disgorgement of Unlicensed Contractor’s     Compensation    23
C.    Other Civil Actions    24
D.    Criminal Penalties    24

VIII.    SUBSTANTIAL COMPLIANCE PROVIDES PROTECTION FROM THE “SWORD” AND THE “SHIELD”    25

IX.    MISCELLANEOUS ISSUES    26
A.    Checking a Contractor’s License    26
B.    Nontransferability of a License    26
C.    Risks of Hiring Unlicensed Contractors    27
D.    Additional Licensing Requirements for Public
        Works Projects    28
E.     Contracting Requirements    28
F.     Advertising Issues    29
G.     Increased Enforcement of License Laws    29

ENDNOTES        30


CHAPTER TWO    38
FUNDAMENTALS OF CONSTRUCTION CONTRACTS    38

I.    BASIC CONTRACT PRINCIPALS    38
A.    Contract Formation    38
1.    Capacity to Contract    38
2.    Consent/Offer and Acceptance    39
a.    Offer    39
b.    Acceptance    39
3.    Lawful Purpose    40
4.    Consideration    40
B.    Contract Interpretation    40
1.    Intent of the Parties    41
2.    Extrinsic Evidence    41
3.    Hand-Written Modifications    41
4.    Meaning of Contract Terms    41
5.    Order of Precedence    42
6.    Implied Obligations    42
C.    Standard Form Contracts    43

II.     RELATIONSHIPS AMONG THE PARTIES – PROJECT     DELIVERY SYSTEMS    45
A.    Design-Bid-Build    45
B.    Design-Build    47
C.    Multi-Prime    48
D.    Construction Management    49
E.    Public Private Partnership    50

III.    PRIME CONTRACT ISSUES    51
A.    Contract Price    51
1.    Lump Sum/Fixed Price    51
2.    Cost Plus Fee    52
3.    Time and Material    52
4.    Guaranteed Maximum Price    53
B.    Scope of “Contract Documents”    53
1.    Contractors are Entitled to Rely on Public
                 Contract Documents    53
C.    Liquidated Damages    55
D.    Changes    55
1.    American Institute of Architects Standard
       Form A201-2007 Article 7    56
E.    Limitations on Delay Damages    56
F.     Differing Site Conditions    59
G.     Contractual Dispute Resolution Procedures    59
1.    Alternative Dispute Resolution Provisions    60
a.        Arbitration    61
b.        Mediation    62
c.        Disputes Review Board    62
H.    Termination    63
1.    Termination for Convenience Clause    63
2.    Default Termination Clause    64
I.    Subcontractor Payment    64

ENDNOTES    66





CHAPTER THREE    68
PUBLIC CONTRACT BIDDING    68

I.    INTRODUCTION TO PUBLIC CONTRACT BIDDING    68    
A.    Purpose    68
B.    Exceptions    69    
C.    Failure to Adhere to Competitive Bidding Procedures    70

II.    PRE-BID PROCEDURES    70
A.    Prequalification    70
B.    Public Disclosure of RFP Proposals    71
C.    Plans and Specifications    71
1.    Adoption of Plans and Specifications    71
2.    Bidder Opportunity to Review Plans    72
3.    Changes to Plans and Specifications    72

III.    BIDDING PROCESS AND BID DOCUMENT
    REQUIREMENTS    72
A.    Requests/Invitation for Bids    72
1.    Contents    72
2.    Alternate Bid Items    75
3.    Amount of Bid Security, Performance and
       Payment Bonds    77
4.    Period of Bid Irrevocability    78
5.    Advertisement/Publication    78    
B.    Instructions for Bidders    78
C.    Bid Forms    79

IV.     BID OPENING/RETURN OF LATE BIDS    80

V.    BID MISTAKE AND WITHDRAWAL    80
A.    Statutory Grounds for Withdrawal    81
B.    Forfeiture of Bid Security     82
C.    Award After Withdrawal or Forfeiture of Bid Security    82
D.    Participation in Re-Bid    83
E.    Subcontractor Bid Mistakes    83
F.    Waiver of Irregularities    84

VI.    EVALUATION AND REJECTION OF BIDS    85
A.    Bid Responsiveness and Responsibility    85            
1.    Responsiveness    85
2.    Responsibility    86
a.    Statutory and Common Law
       Definitions    86
b.    Relative Superiority Analysis
       Prohibited    87
c.    Hearing/Due Process    87
B.    Subcontractor Listing Law    88
1.    Subcontractor Substitution    89
2.    Subcontractor Case Law    89
a.    Unlicensed Subcontractors    89
b.    Subcontractor Legal Actions Against
       Prime    90
C.    Bid Protests    91
1.    General    91
2.    Bid Protest Procedures    93
3.    Judicial Remedies    94
a.    Writ of Mandate    94
b.    Monetary Damages    95
c.    Injunctive Relief    95
4.    Judicial Review of Bid Protests    95

VII.    PROJECT DELIVERY METHODS    96
A.    Design-Bid-Build vs. Design-Build    97
1.    Design-Bid-Build    97
2.    Design-Build    98
B.    Construction Management    100
C.    Multiple Prime Contracting    101
1.    Advantages    101
2.    Disadvantages    101
D.    Job Order/Annual Contracts    102

VIII.    SELECTION OF DESIGN PROFESSIONALS    103
A.    Statutory Requirements    103
B.    Design Services Contracts    104
1.    Public Contract Code Section 20103.6
       Disclosure of Indemnification Provision    104
2.    Further Limits on Indemnity Provisions for         
       Design Professionals    105

IX.    CONCLUSION    105

ENDNOTES    107



CHAPTER FOUR     110
COMMON CONTRACT DISPUTES    110

1.    COMMON OWNER BREACH    110
A.    Owner’s Wrongful Non-Payment    110
B.    Owner-Caused Delay     111
1.    Categorizing the Delay     112
2.    Contractor’s Burden of Proof for Delay
       Claims    116
3.    Recoverable Delay Damages    117
a.    Direct Costs    117
b.    Idle Time/Equipment    118
c.    Extended Field and Home Office
       Overhead    118
d.    Increased Costs for Labor and
       Materials    118
e.    Lost Profits    119
f.     Impeded Access to Project    120
C.    Defective or Incomplete Plans and Specifications    121
1.    Design Errors and Omissions and the Effect
       On Performance    122
2.    Determination of Design Errors and
       Omissions    123
D.    Acceleration by Owner    124
1.    Types of Acceleration    124
2.    Impact and Costs    126
3.    Notice to Owner    126
E.    Wrongful Termination by Owner    126
1.    Termination in General     126
2.    Types of Termination    127
3.    Wrongful Termination    128
4.    Recoverable Damages    130

II.    COMMON CONTRACTOR BREACH    132
A.    Performance    132
1.    Defective or Non-Conforming Work    132
a.     Contractor’s Non-Compliance with
        Contract Documents    132
b.     Recoverable Damages    133
c.    Theories of Liability     133
2.     Delayed Performance    134
a.    Types of Delay     134
b.    “Abandonment” Versus “Substantial Completion”    135
c.    Recoverable Delay Damages    136    
B.     Non-Payment of Subcontractors/Suppliers    138
C.     Suspended/Revoked Licensure    138

ENDNOTES    140


CHAPTER FIVE    143
CHANGE ORDERS AND EXTRA WORK    143

I.     THE CHANGE ORDER CLAUSE    143
A.    The Purpose of the Change Order Clause    143
B.    The Rights and Obligations Created by the
        Change Order Clause    144
C.    The Importance of Following the Contractual Change
        Order Procedures    144

II.    TYPES OF CHANGES    145
A.    Actual or Owner Acknowledged Changes    145
B.    Constructive Changes    146
C.    Cardinal Changes    146

III.    THE CHANGE ORDER    146
A.    The Change Order Form    146
B.    Disputes Over Change Order’s Scope of Work    147
C.    Pricing the Change Order    147
D.    Authority to Issue Change Orders    149    
1.    Private Projects    150
2.    Public Projects    150
E.    Releases and Reservations in Change Order Forms    151

IV.     PROCEEDING UNDER PROTEST    151
A.    Compliance with Contractual Notice and
        Documentation Requirements    152
B.    Documenting Cost and Time Impacts    152

V.    ORAL CHANGES: WAIVER OF THE WRITING     REQUIREMENT    153
A.    Private Contracts    153
B.    Public Contracts    154

VI.        VALIDITY OF CHANGE ORDERS ISSUED AFTER
    THE CHANGED OR EXTRA WORK IS PERFORMED    156

VII.        A CHANGE ORDER IS NOT REQUIRED TO
    RECOVER FOR EXTRA WORK CAUSED BY
    OWNER’S BREACH OF THE IMPLIED WARRANTY
    OF CORRECTNESS OF PLANS AND
    SPECIFICATIONS    156

VIII.    IMPLICATIONS OF CALIFORNIA’S FALSE
    CLAIM ACT ON CHANGE ORDERS    157

IX.            MATERIAL CHANGES: THE DOCTRINES
    OF ABANDONMENT OF CONTRACT AND
    CARDINAL CHANGES    158
A.    Abandonment of Contract    158
1.    Private Contracts    158
2.    Public Contracts    159
B.     Cardinal Change    160
C.     Total Cost or Modified Total Cost Measure of
         Damages    160

ENDNOTES    162


CHAPTER SIX    164
TYPES OF CONSTRUCTION CLAIMS    164

I.     OWNER CLAIMS    165
A.    Delay    165
1.    Types of Delay    165
a.    Excusable vs. Inexcusable Delay    165        
b.     Compensable vs. Non-Compensable
         Delay    166
c.     Concurrent Delay     166
2.     Viability of Recovering for Delay     166
a.    Liquidated Damages    167
b.    Ownership of Float    167
B.     Failure to Perform    168
1.    What Constitutes a Failure to Perform    168
2.     Viability of Recovering for Failure to
        Perform    169
a.    Owner’s Breach of Implied
       Warranty    169
b.    Waiver by Owner    170
C.    Breach of Warranty    170
1.    Types of Warranties    170
2.    Viability of Recovering for Breach of
        Warranty    171
D.     Termination    171
1.    Types of Termination    171
a.    Termination for Convenience    171
b.    Termination for Default    172
2.    Viability of Recovering for Termination    172
E.     False Claims    173
1.    What Constitute a False Claim    173
2.    Viability of Recovering for False Claims    173
F.     Disgorgement/Licensing    174
1.    California’s Licensing Requirements    174
2.    Penalties for Failing to Comply with
       California’s Licensing Requirements    175

II.    CONTRACTOR CLAIMS    175
A.    Delay    175
1.    Identifying Delays    175
2.    Viability of Recovering for Delay    176
3.    No Damages for Delay Provisions    177
B.    Acceleration    178
1.    What Constitutes Acceleration    178
2.    Viability of Recovering for Acceleration    178
C.    Disruption and Productivity Impacts    179
1.    What Constitutes Disruption or
       Productivity Impacts    179
2.    Viability of Recovering for Disruption and
       Productivity Impacts    179
D.    Changed/Extra Work and Differing Site
        Conditions    180
1.    Changed/Extra Work    180
a.    Actual Changes    181
b.    Constructive Changes    181
c.    Cardinal Changes    181
d.    Contractor’s Duty to Proceed    182
2.    Differing Site Conditions    182
a.    What Constitutes a Differing Site
       Condition    182
b.    Contractual and Legal Allocation of Risk
        for Differing Site Conditions    183
3.     Contractor’s Claim for Owner’s Breach of
        Implied Warranty of Correctness of Plans and
        Specifications    184
E.     Failure to Make Payments    184
1.    Types of Payment Made to the Contractor    184
a.    Progress Payments    185
b.    Retention/Final Payment    185    
2.    Time Period for Payment and Prompt Payment
       Statutes        185
3.    Contractor’s Ability to Cease Performance
       Based on the Owner’s Failure to Make Progress
       Payments    187
F.     Suspension of Work/Stop Work Notice    188
1.    What Constitutes Suspension of Work/Stop
       Work Notice    188
2.    Viability of Recovering for Suspension of
       Work/Stop Work Notice    188
G.     Termination    189
1.    Types of Termination    189
a.    Actual Termination    189
b.    Constructive Termination    189
2.    Viability of Recovering for Termination    190

III.    CONCLUSION    190

ENDNOTES    191


CHAPTER SEVEN    196
TYPES OF RECOVERABLE COSTS/DAMAGES    196

I.    INTRODUCTION    196

II.    BREACH OF CONTRACT DAMAGES    196
A.    Measure of Damages    196
B.    Direct vs. Consequential Damages    197
C.    Mitigation of Damages    197
D.    Recoverable Damages for Typical “Owner” Claims    198
1.    Contractor’s Failure to Perform According to
        Plans and Specifications    198
2.    Contractor’s Failure to Complete Work    199
3.    Owner’s Rightful Termination of Contractor    199
4.    Liquidated Damages    199
5.    Contractor-Caused Delay    200
E.    Recoverable Damages for Typical “Contractor”
       Claims        200
1.    Extra Work     200
2.    Owner’s Defective Plans and Specifications    200
3.    Owner-Caused Time-Related Damages    201
4.    Owner’s Wrongful Termination of Contractor    201
5.    Lost/Impaired Bonding Capacity    202
6.    Profit    203
7.    Lost Future Profits    203
8.    Other Claims    204
F.    Other Damages Associated with Breach of Contract
       Claims    204
1.    Punitive Damages    204
2.    Interest    205
a.    Pre-judgment    205
b.    Post-judgment    206
c.    Prompt Payment Statutes    206
3.    Attorneys’ Fees    206
a.    American Rule    206
b.    Mutuality of Remedy    207
c.    Indemnification Provision or
       Attorney Fees Provision    207
d.    Attorney Fees as Consequential
       Damages    208
e.    Statutes    209

III.    TORT DAMAGES    209
A.    Measure of Damages    209
B.    Commonly Asserted Torts in Construction Disputes    210
1.    Fraud    210
2.    Interference with Contractual Relationship    210
3.    Interference with Prospective Economic
       Relations    211
4.    Design Professional Negligence    211
C.    Other Damages Associated with Tort Claims    211
1.    Punitive Damages    211
2.    Interest    212
3.    Attorneys’ Fees    212

IV.    CONCLUSION    212

ENDNOTES    213


CHAPTER EIGHT    218
CALCULATING AND PROVING DAMAGES    218

I.    INTRODUCTION    218

II.    METHODS OF CALCULATION    219
A.    Actual Cost Method    219
B.    Total Cost Method    219
C.    Modified Total Cost Method    220
D.    Quantum Meruit    221
E.    Jury Verdict Method    222

III.    DIRECT COSTS    223
A.    Labor Costs    223
1.    Direct Labor Overrun    223
a.    Additional Labor Hours    223
b.    Determination and Application of Wage
       Rates    223
c.    Labor Burdens    223
2.    Labor Escalation    224
3.    Lost Productivity    224
a.    Reasons for Lost Productivity    224
b.    Calculating Lost Productivity    224
i.    “Measured Mile” Analysis    224
ii.    Comparison to Similar
                 Contracts    225
iii.    Project Productivity Studies    225
iv.    Industry Standards and
                  Manuals    226
v.    Expert Analysis    226
vi.    Bid Comparisons    226
vii.    Actual vs. Anticipated
                  Manloading Studies    226
B.    Material Costs    227
1.    Reasons for Material Cost Claims    227
2.    Other Associated Costs    227
3.    Calculating Additional Material Quantities    228
4.    Calculating Additional Material Costs    228
C.    Equipment Costs    229
1.    Determining Additional Usage    229
a.    Recording Additional Hours    229
b.    Productivity of Equipment and
                 Quantity of Work    229
c.    Additional Contract Time    230
d.    Correlation to Manhours    230            
e.    “Modified” Total Usage    230
f.    Standby/Idle Time    231
2.    Cost of Equipment    231
a.    Actual Cost    231
b.    Outside Rentals    232
c.    Intra-Company Charges    232
d.    Industry Guides    232
e.    State and Local Compilations    233

IV.     OTHER DIRECT COSTS    233
A.    Insurance    233
B.    Bond Premiums    233

V.    OVERHEAD COSTS    233
A.    Jobsite Overhead    234
B.    Home Office Overhead    234

VI.    PROFIT    235

VII.    DELAY DAMAGES    236
A.    Basis and Proof of Delay Damages    236
B.    Escalation Costs    236
C.    Extended Performance Costs    236
1.    Idle Labor    237
2.    Idle Equipment    237
3.    Jobsite Overhead    237
4.    Home Office Overhead    237

VIII.    CONCLUSION    238

ENDNOTES    240


CHAPTER NINE    244
CALIFORNIA PUBLIC WORKS CLAIM PROCEDURES    244

I.    CONTRACTUAL CLAIM PROCEDURES    244

II.    STATUTORY CLAIM PROCEDURES    244
A.    State Contract Act    244
1.    No Government Code Claim Required by
       Statute    245
2.    Arbitration    245
a.    Time to Initiate    245
b.    Arbitration Procedures    246
i.    Commencing Arbitration    246
ii.    Selection of Arbitrators    247
iii.    Discovery    247
iv.    Motions, Hearings and Award    247    
B.    Government Code Claims    248
1.    Filing a Claim    248
a.    Time to File Claim    248
b.    Amendment of Claim    249
c.    Presentation of Claims    249
2.    Contents of Claim    249
3.    Public Entity Response    250
a.    Notice of Insufficiency of Claim    250
b.    Action by Public Entity on Claim     251
c.    Notice of Rejection of Claim    251
4.    Filing Suit on Claim    252
C.    Local Public Entity Claims Less Than $375,000    252
1.    Definition of a “Claim”    252
2.    Submission of the Claim    253
3.    Procedure Following Submission of Claim    253
a.    Time for Public Agency Response    253
i.    Claims Under $50,000    253
ii.    Claims Over $50,000    253
b.    Claimant’s Demand for a Meet and
                 Confer Conference    253
c.    Filing a Claim Pursuant to the
                 Government Contract Code    254
4.    Statutory Mediation and Arbitration
                 Procedures        254
a.    Non-Binding Mediation    254
b.    Non-Binding Arbitration    254
5.    Court Trial    254
6.    Undisputed Portion of Claim; Interest    255

III.    CALIFORNIA FALSE CLAIMS ACT    255
A.    “False Claim” Defined    255
B.    Materiality of the False Claim    257
C.    Civil and Criminal Penalties    257
D.    Public Enforcement    257
E.    Private Enforcement    257
F.    Voluntary Disclosure    258

ENDNOTES    259


CHAPTER TEN    262
PRESERVING THE RIGHTS TO PAYMENT – MECHANIC’S
LIEN, STOP PAYMENT NOTICE, PAYMENT AND
PERFORMANCE BOND    262

I.    SUMMARY OF REMEDIES    262

II.    MECHANIC’S LIENS    262
A.    Nature of Mechanic’s Lien Remedy    262
1.    Foreclosure as Ultimate Remedy    262
2.    Practice Tip: Mechanic’s Lien as Leverage    263
B.    Proper Claimants    263
C.    Priority Issues    264
1.    First-in-Time Rule    264
2.    Mechanic’s Lien Priority Relates Back to
                 Commencement of Work    264
3.    Super-Priority of Site Improvement Liens    265
4.    Standard Priority for Designer’s Liens    266
5.    Optional Advances of Construction Lender    267
D.    Preliminary Notice    267
1.    Purpose and Description    267
2.    Required Elements    267
3.    Claimants Required to Serve    268
a.    Practice Tip: Prime Contractors Should
       Serve a Preliminary Notice    268
4.    Mechanics of Proper Service    268
5.    Effect of Failure to Serve    269
E.    Notice of Mechanic’s Lien    269
F.    Recordation    270    
1.    Contents of Mechanic’s Lien    270
2.    Timing of Recordation    270
a.    Deadline for Recording a Mechanic’s
                 Lien    270
b.    Earliest Time for Recording a
                 Mechanic’s Lien    271
3.    Amount of Lien    272
a.    Delay Damages    272
b.    Stored Materials    272
c.    Attorneys’ Fees    273
d.    Interest    273
G.    Lis Pendens    273
H.    Notice of Non-Responsibility    273
1.    Purpose and Description    273
2.    Participating Owner Exception    274

III.    SPECIAL ISSUES INVOLVING DESIGN WORK    274
A.    Designers May File Mechanic’s Liens    274
B.    Pre-Construction Designer’s Liens    274
1.    Special Requirements    275
a.    Pre-Lien Notice of Breach    275
b.    Same Owner Rule    275
c.    Government Approval Rule    275
2.    Ordinary Priority Rights    275
3.    Expiration Upon Construction    276
C.    Filing Suit to Enforce Mechanic’s Liens    276
D.    Removing Mechanic’s Liens    276
1.    Summary Proceedings to Remove Mechanic’s
       Lien    276
a.    Petition to Release Mechanic’s Lien:
                Civil Code Section 8480    277
b.    Motion to Expunge: Code of Civil
                Procedure Section 405.30 et seq.    277
2.    Mechanic’s Lien Release Bonds    277
3.    Waiver and Release Forms    278
a.    Civil Code Releases    278
b.    Practice Tip: Collection of Releases
                 for Recording Purposes    278
c.    Practice Tip: Collection of Lien
                 Releases With Payment Applications    278

IV.    STOP PAYMENT NOTICES    279
A.    Nature of Stop Payment Notice Remedy    279
B.    Private Works    279
1.    Proper Claimants    279
2.    Preliminary Notice    279
3.    Contents of Stop Payment Notice    279
4.    Timing and Manner of Service    280
5.    Effect of Bonded vs. Unbonded Stop Payment
       Notice    280
a.    Creation of Mandatory Duty to
                 Withhold    280
b.    Recovery of Attorneys’ Fees and
                 Interest    280
c.    Practice Tip: Serving a Bonded Stop
                 Payment Notice    281
6.    Filing Suit    281
7.    Assignment of Loan Proceeds    281
8.    Effect of Payment Bond    281
C.    Public Works    282
1.    Proper Claimants    282
2.    Preliminary Notice    282
3.    Contents of Stop Payment Notice    282
4.    Timing and Manner of Service    282
5.    Filing Suit    283

V.    PAYMENT BONDS    283
A.    Nature of Payment Bond Remedy    283
B.    Preliminary Notice    283
C.    Statute of Limitations    284
1.    Public Works of Improvement    284
2.    Private Works of Improvement    284
D.    Bond Notice Exception to Preliminary
        Notice Requirement    284
1.    Practice Tip: Direct Contractors Must be
       Vigilant to Reduce Exposure to “Latent”
       Payment Bond Claims    284
E.    Defenses    285
1.    Surety-Specific Defenses    285
a.    Alternation of the Bonded Obligation    285
b.    Requiring Pursuit of Other Securities    286
2.    Surety’s Right to Assert Defenses of Principal    286

VI.    PERFORMANCE BONDS    286
A.    Nature of Performance Bond Remedy    286
B.    Prerequisites    287
1.    Declaring Direct Contractor in Default    287
2.    Notice to Surety    287
C.    Defenses    287
1.    Surety-Specific Defenses    288
a.    Material Alterations to Bonded
                Contract Without Surety’s Consent    288
b.    Overpayment    288
c.    Failure to Permit Investigation    289
2.    Surety’s Right to Assert Defenses of Principal    289
D.    Scope of Exposure    289
1.    Completion Costs    289
2.    Delay Damages    289
E.    Statute of Limitations    290

ENDNOTES    291


CHAPTER ELEVEN    295
SURETY    295

I.    INTRODUCTION    295

II.    CREATING THE SURETYSHIP RELATIONSHIP    296
A.    Purpose: Answering for the Debt of Another    296
B.    Formation of the Indemnity Agreement    296
1.    Indemnity Clause    297
2.    Collateral Securing Obligation    297
3.    Right to Settle    298
C.    Arguments Against Indemnity    299
D.    Surety’s Rights to Subrogation    299

III.    TYPES OF BONDS USED IN CONSTRUCTION
    INDUSTRY    301
A.    Performance Bonds    301
B.    Labor and Materials Payment Bonds    301
C.    Indemnity Bonds    302
D.    Subdivision Bonds    302
1.    Subdivision Bonds Versus Traditional Public
                 Works Bonds    303
E.    Bid Bonds    304

IV.    OVERVIEW OF PERFORMANCE BOND CLAIMS    305
A.    Statutes Requiring Performance Bonds; Minimum
        Amounts    305
B.    Types of Damages Covered    306
1.    Liquidated Damages    306
2.    Attorneys’ Fees    306
3.    Breach of Implied Good Faith and Fair
       Dealing    307
C.    Statute of Limitations    307

V.     OVERVIEW OF PAYMENT BOND CLAIMS    308
A.    Payment Bonds on Public Projects    308
1.    Statutes Requiring Payment Bonds; Minimum
                 Amounts    308
2.    Prerequisites    309
3.    Notice Requirements    309
4.    Statute of Limitations    310
5.    Recoverable Damages    310
B.    Payment Bonds on Private Projects    311
1.    Statutes Requiring Payment Bonds; Minimum
       Amounts    311
2.    Prerequisites    311
3.    Notice Requirements    311
4.    Statute of Limitations    312
5.    Recoverable Damages    312
C.    Payment Bonds on Federal Projects    313
1.    Statutes Requiring Payment Bonds; Minimum
       Amounts    313
2.    Prerequisites    313
3    Notice Requirements    313
4.    Statute of Limitations    314
5.    Recoverable Damages    314

VI.    OPTIONS AVAILABLE TO SURETY UNDER
    PERFORMANCE BOND CLAIM    315
A.    Takeover and Complete Bonded Project    315
B.    Tender to New Contractor    315
C.    Indemnity Bond Obligee    316
D.    Finance Bond Principal’s Completion of Bonded
        Project    316    
E.    Relinquish Bond Penal Sum    317
F.    Deny Claim    317

VII.     SCOPE OF SURETY’S OBLIGATION UNDER PAYMENT
    BOND    317
A.    Intended Coverage    317
B.    Types of Payment Bonds    318
1.    Public Bonds    318
2.    Private Bonds    319
C.    Scope of Coverage    320

VIII.    DEFENSES AVAILABLE TO SURETY AGAINST BOND CLAIMS    320
A.    Failure to Satisfy Condition Precedent    320
B.    Material Alteration    321
C.    Early/Advanced Payments    321
D.    Statute of Limitations    321
E.    Fraud or Misrepresentation    322

IX.    CONCLUSION    322

ENDNOTES    324


CHAPTER TWELVE    328
PREVAILING WAGE AND LABOR ISSUES    328

I.    INTRODUCTION    328
A.    Scope of Chapter    328
B.    California Employment Laws    329

II.    PREVAILING WAGE    330
A.    Introduction    330
B.    Purpose of Prevailing Wage Laws    331
C.    State and Federal Prevailing Wage Laws    331
D.    Public Works Projects    331
E.    Prevailing Wage Rates    334
F.    Payment of Prevailing Wages    335
G.    Responsibility for Payment of Prevailing Wages    336
H.    Liability for Violations of Prevailing Wage Laws    338
I.     Enforcement of Prevailing Wage Laws    340

III.     UNIONS    342
A.    Introduction    342
B.    Project Labor Agreements    343
C.    Strikes    343
D.    Picketing    344

IV.    WORKERS’ COMPENSATION    346
A.    Introduction    346
B.    Insurance/Coverage Issues    346
C.    Additional Claim Types    346
D.    Preemption Defense    347

V.    UNFAIR COMPETITION    347
A.    Introduction    347
B.    Trade Secrets    348
C.    Covenants Not To Compete    349
D.    Solicitation of Clients and Employees    350

VI.    LAYOFFS    352
A.    Introduction    352
B.    Worker Adjustment and Retraining Notification Act     (“WARN”)    352

VII.    CONCLUSION    355

ENDNOTES    356


CHAPTER THIRTEEN    361
RISK MANAGEMENT AND INSURANCE    361

I.    INTRODUCTION – RISK MANAGEMENT ON CONSTRUCTION PROJECTS    361
    
II.    AVOIDANCE    361
A.    Scope of Work and Exclusions    362
B.    Loss Prevention Programs    362
1.    Right to Repair    363
C.    Portfolio and Job Selection Management    364

III.    TRANSFER    365
A.    Indemnity Agreements    365
B.    Waiver and Releases    367
C.    Liquidated Damages Provisions    368
D.    Environmental Liability Transfers    369
E.    Notice Provisions    372
F.    Liability Shifting Upon Project Turnover    373

IV.    LIMIT    373
A.    Limitations of Liability    373
B.    Consequential Damage Waivers    373
C.    Contractual Limitations on Commencement of Actions    375
D.    Alternative Dispute Resolution    375
E.    Limitations of Remedies    376

V.    INSURE – THE ROLE OF INSURANCE ON
    CONSTRUCTION PROJECTS    376
A.    Typical Insurance Products for Construction Projects    376
1.    Workers’ Compensation    376
2.    Builders Risk    377
3.    General Liability     378
4.    Design Errors and Omissions    380
B.    Novel Approaches to Project Insurance    380
1.    Wrap-ups; OCIPs; CCIPs    380
2.    Project Specific Policy Considerations    381
3.    Subcontractor Default Policies    381
4.    Cost Cap Insurance    382

ENDNOTES    383


CHAPTER FOURTEEN    385
GREEN CONSTRUCTION AND BUILDINGS    385

I.     WHAT IS GREEN CONSTRUCTION    385
A.    Definitions    386
B.    The Green Construction Market    387
C.    A Growing Market    388

II.    IMPACTS BUILDINGS HAVE ON THE
    ENVIRONMENT    389
A.    General Statistics Regarding the Effect of Buildings
        on the Environment    389
B.    Energy, Water and Land Use    390
C.    Indoor Environmental Quality and Effects    391
D.    Materials, Waste and Storm Water Runoff    392

III.     RATING AND CERTIFICATION SYSTEMS FOR SUSTAINABLE DESIGN AND CONSTRUCTION    393
A.    LEED and the United States Green Building Council    393
1.    LEED Rating System    393
2.    Documentation    394
3.    New Construction and Renovations    395
B.    Legal Challenge to USGBC Performance Claims and
        Statistics    395
C.    Growth of LEED    396
D.    Other Organizations and Rating Systems    396

IV.     CODE REQUIREMENTS AND GREEN BUILDING    397
A.    California Green Building Standards Code
       (CALGreen)    397
B.    Enforcement and Recognition Under CALGreen    399
C.    Local Green Building Codes    400
1.    Cities    400
2.    Prescriptive Measures and Performance
       Standards    401
3.    Enforcement    402

V.    CONTRACTUAL RISK ALLOCATION AND
    LITIGATION    403
A.    Application of the “Spearin Doctrine”    403
1.    Performance and Design Specifications    404
2.    Liability for Failing to Meet a Specified
       Standard    404
B.    Green Contract Issues    406
C.    Standard Form Contracts    408
D.    Green Building Litigation    409

VI.    CONCLUSION    410

ENDNOTES    412    

TOP