ALABAMA

 

About the Author  |  This Book's Table of Contents  |  Order this Book  |  Seminars  |  Sponsors  |  Return to Map

ALABAMA CONSTRUCTION LAW
TABLE OF CONTENTS
 

CHAPTER ONE:  The Owner

1.0   INTRODUCTION
1.1   FINANCING THE CONSTRUCTION PROJECT
1.2   PAYMENT
1.2.1    Lien Waivers

1.2.2    “Pay-if-Paid” and “Pay-when-Paid” Clauses

1.2.3    Retainage

1.3   OWNER OBLIGATIONS
1.3.1    Implied Obligations and Contracts Implied by Law

1.3.2    The Spearin Doctrine

1.4   RISK ALLOCATION AND SHIFTING
1.4.1    Indemnity Provisions

1.4.2    Insurance

1.5   SUBSTANTIAL COMPLETION, PUNCH LIST AND FINAL COMPLETION
1.5.1    Substantial Completion

1.5.2    Punch List Items

1.5.3    Final Completion

1.5.4    Owner Termination Provisions

1.5.4.1    Termination for Convenience

1.5.4.2    Termination for Cause

1.5.5    Venue Provisions



CHAPTER TWO:  The Contractor

2.0   INTRODUCTION
2.1   LICENSURE
2.1.1    The Licensure Process

2.1.2    Qualification with the Alabama Secretary of State and Obtaining Local Business Licenses

2.1.3    General Contractor and Subcontractor Defined

2.1.4    Bidding and Prohibited Efforts to Circumvent Licensure Requirements

2.1.5    Bidding on Private Projects

2.2   CONVENTIONAL CONSTRUCTION CONTRACTS
2.2.1    Type of Contract and Amount

2.2.1.1    Lump Sum Contracts

2.2.1.2    Cost Plus Contracts

2.2.1.3    Cost Plus a Fee with a Guaranteed Maximum Price

2.2.1.4    Unit Price Contracts

2.2.2    Scope of Work

2.2.3    Schedule of Values

2.2.4    Construction Schedule

2.2.5    Delay Provisions

2.2.5.1    Typical Owner-Contractor Delay Provisions

2.2.5.2    Liquidated Damages Provisions

2.2.5.3    No Damage for Delay Provisions

2.2.6    Indemnity and Insurance

2.2.6.1    Introduction

2.2.6.2    Breadth of Indemnity Provisions

2.2.6.3    Insurance Requirements and Additional Insured Status

2.2.7    Limitation of Liability and Consequential Damages Waiver Provisions

2.2.7.1    Limitation of Liability Provisions

2.2.7.2    Consequential Damages Waivers

2.2.8    Responsibility for Permits and Fees

2.2.9    Change Orders and Construction Change Directives

2.2.9.1    Introduction

2.2.9.2    Rights Afforded Under Change Order Clauses

2.2.9.3    Change Order Protocol

2.2.9.4    Construction Change Directives

2.2.10    Order of Precedence and Battle of the Forms Provisions

2.2.11    Site Conditions Provisions

2.2.11.1    Site Visits

2.2.11.2    Limitation of Liability for Site Conditions

2.2.12    Code Compliance

2.2.12.1    Limitation of Liability

2.2.13    Contractor’s Warranty

2.2.13.1    Express Warranties

2.2.13.2    Implied Warranties



CHAPTER THREE:  Public Construction

3.1   INTRODUCTION
3.2   FEDERAL GOVERNMENT CONTRACTING
3.3   STATE AND LOCAL CONTRACTING
3.3.1    Competitive Bidding

3.3.1.1    Bid Solicitation and Pre qualification

3.3.1.2    Bid Selection

3.3.1.3    Bid Bonds

3.3.2    Enforceability of Bids

3.3.2.1    Contractor Bids

3.3.2.2    Bid Errors

3.3.2.3    Subcontractor and Supplier Quotations

3.3.3    Post-Award Relief

3.4   BID PROTESTS
3.5   CONTRACT AWARD
3.6   PERFORMANCE OF PUBLIC WORKS CONTRACTS
3.6.1    Contract Documents

3.6.2    Payment Issues

3.6.3    Change Orders

3.6.4    Disputes



CHAPTER FOUR:  Building Codes, Standards, and Permits

4.1   INTRODUCTION
4.2   TYPES OF GOVERNING CODES
4.2.1    State Requirements

4.2.2    Local or Municipal Requirements

4.3   BUILDING PERMITS
4.4   BUILDING INSPECTIONS AND CERTIFICATES OF OCCUPANCY


CHAPTER FIVE:  The Architect/ Engineer

5.1   INTRODUCTION
5.2   STATE LAWS GOVERNING THE PRACTICE OF ARCHITECTURE & ENGINEERING
5.2.1    Statutory Regulation of Architects

5.2.2    Statutory Regulation of Engineers

5.2.3    Associations of Architects and/or Engineers

5.3   OWNER-ARCHITECT/ENGINEER AGREEMENT
5.3.1    Types of Agreements

5.3.2    Limitation on Services

5.3.3    Additional Services

5.4   ARCHITECT-CONSULTANT AGREEMENTS
5.5   THE ARCHITECT/ENGINEER’S RESPONSIBILITIES
5.5.1    Design

5.5.2    Bidding and Negotiation

5.5.3    Construction Administration

5.5.3.1    “Inspection”

5.5.3.2    Review of Applications for Payment

5.5.3.3    Review and Approval of Contractor Submittals

5.5.3.4    Authority to Order Changes

5.5.3.5    The Architect as Judge

5.5.4    Post-Construction

5.6   THE ARCHITECT ENGINEER'S LIABILITY
5.6.1    Liability to the Owner

5.6.2    Liability to the Contractor

5.6.2.1    Inadequate Plans and Specifications

5.6.2.2    Negligent Construction Administration

5.6.3    Liability to Subcontractors

5.6.4    Liability to Other Third Parties

5.6   PROFESSIONAL LIABILITY INSURANCE


CHAPTER SIX:  The Subcontractor

6.1   INTRODUCTION
6.2   OWNER’S TYPICAL CONTRACT OBLIGATIONS
6.2.1    Duty of Payment

6.2.2    Duties of Cooperation and Disclosure

6.3   OWNER’S IMPLIED OBLIGATIONS
6.3.1    Warranty of Plans and Specifications

6.3.2    Duty Not to Delay, Hinder or Interfere With the Contractor’s Performance

6.4   OWNER’S MATERIAL CHANGE IN CONTRACT
6.5   DISCLAIMER OR WAIVER OF OWNER’S OBLIGATIONS


CHAPTER SEVEN:  Changes in the Work

7.1   INTRODUCTION
7.2   CONTRACT TERMS FOR CHANGES
7.3   CHANGE PROTOCOL
7.4   WHEN IS EXTRA COMPENSATION DUE?
7.5   CARDINAL CHANGES
7.6   “DIRECTED CHANGE” OR “FORCE ACCOUNT” CLAUSES
7.7   UNDOCUMENTED ORAL CHANGE ORDERS
7.8   CHANGES DUE TO DEFECTIVE PLANS AND SPECIFICATIONS
7.9   CONSTRUCTIVE CHANGES
7.10   ADDITIONAL, UNAUTHORIZED OR NON-CONFORMING WORK
7.11   CHANGES BY OUTSIDE FORCES


CHAPTER EIGHT:  Site Conditions

8.1   INTRODUCTION
8.2   TYPES OF SITE CONDITIONS
8.3   RESPONSIBILITY/DISCLAIMERS
8.4   NOTICE


CHAPTER NINE:  Damages

9.1   OTHER DAMAGES
9.1.1    Owner’s Damages for Contractor’s Inadequate or Incomplete Performance

9.1.2    Contractor’s Damages

9.1.2.1    Contractor Damages for Owners’ Late Payment

9.1.2.2    Contractor Damages for Owner’s Termination of Project

9.2   ATTORNEY’S FEES
9.3   PREJUDGMENT INTEREST
9.4   PUNITIVE DAMAGES
9.5   EXCLUSIONS AND LIMITATIONS ON RECOVERABLE DAMAGES
9.5.1    “No Damages for Delay” Clauses

9.5.2    Monetary Limitations

9.5.3    Waivers of Consequential and other Damages

9.5.4    Duty to Mitigate Damages



CHAPTER TEN:  Bonds

10.1   INTRODUCTION
10.2   A CONTRACTOR’S RIGHT TO RELY ON THE OWNER’S REPRESENTATION OF CONDITIONS
10.2.1    Duty to Investigate Site

10.2.2    Duty to Disclose

10.2.3    Disclaimers

10.3   NOTICE
10.4   CONTRACTUAL REMEDIES
10.4.1    Type I Conditions

10.4.2    Type II Conditions

10.4.3    Hazardous Materials

10.5   SITE CONDITIONS NOT COVERED BY THE “DIFFERING SITE CONDITIONS” CLAUSE
10.6   COMPENSATION
10.7   BONDS AND LIENS IN PUBLIC CONTRACTING – THE MILLER ACT
10.7.1    Introduction

10.7.2    The Federal Miller Act – Making a Claim on a Federal Project

10.7.2.1    Purpose and Reach of the Miller Act

10.7.2.2    Materials and Equipment

10.7.2.3    Process for Asserting a Miller Act Claim

10.7.2.3.1    Time periods in which to assert claims

10.7.2.3.2    Notice Requirements

10.7.2.3.3    Initiating a Lawsuit to Perfect the Miller Act Claim

10.7.2.3.4    Arbitrability of Miller Act Claims

10.7.2.3.5    Contractual Waiver of Miller Act Claims

10.7.2.3.6    Recovery of Attorneys’ Fees

10.7.2.4    Payment of Successful Bond Claims

10.7.3    Alabama’s Little Miller Act – Making a Claim on State, County and Municipal projects

10.7.3.1    Bond Requirements

10.7.3.2    Who is Afforded Protection Under the Little Miller Act

10.7.3.3    What is Covered?

10.7.3.3.1    Labor and Materials

10.7.3.3.2    Necessary Rental Equipment and Items Consumed During the Work

10.7.3.3.3    Repairs Necessary for Completion of the Project

10.7.3.3.4    Freight and Storage Expenses

10.7.3.4    Mandatory Notice Requirement

10.7.3.5    Venue for Little Miller Act Claims

10.7.3.6    Parties to a Little Miller Act Claim

10.7.3.7    Limitations Period



CHAPTER ELEVEN:  DAMAGES AND DELAYS
11.1     INTRODUCTION
11.2     DELAY AND ITS CONSEQUENCES
            11.2.1  Classification of Delays
                       11.2.1.1   Excusable Delay
                       11.2.1.2   Compensable Delay
                       11.2.1.3   Inexcusable Delay
                       11.2.1.4   Concurrent Delay
                       11.2.1.5   Critical Delay
            11.2.2  Consequences of Delay
11.3     CONTRACTUAL DELAY AND SCHEDULING
            PROVISIONS
11.4     REMEDIES FOR DELAYS
            11.4.1  Owner Remedies
            11.4.2  Contractor Remedies
11.5     PROOF AND RECOVERY OF DAMAGES FOR DELAY
11.5.1  Methods of measuring and Proving Delays
11.5.2  Types of Delay Damages
            11.5.2.1   Classification of Damages
            11.5.2.2   Contractors’ Delay Damages
            11.5.2.3   Owners’ Delay Damages
            11.5.2.4   Pricing and Proof of Damages
11.6     OTHER DAMAGES
            11.6.1  Owners’ Damages for Contractors’ Defective or Incomplete Performance
                        11.6.1.1   Types of Damages
                        11.6.1.2   Measure of Damages
            11.6.2  Contractors’ Damages
                        11.6.2.1   Types of Damages
                        11.6.2.2   Late Payment Damages
                        11.6.2.3   Termination Damages
11.7     ATTORNEYS’ FEES
11.8     PREJUDGMENT INTEREST
11.9     PUNITIVE DAMAGES
11.10   EXCLUSIONS OR LIMITATIONS OF DAMAGES
            11.10.1   “No Damages for Delay” Clauses
            11.10.2   Monetary Limitations
            11.10.3   Waivers of Consequential and Other Damages
            11.10.4   Duty to Mitigate Damages

CHAPTER TWELVE:  BONDS
12.1     INTRODUCTION
12.2     CONTRACTOR BONDS
            12.2.1  Federal Projects – The Miller Act
            12.2.2  State Public Works – The “Little Miller Act”
            12.2.3  Performance Bonds
            12.2.4  Payment, or Labor and Materials, Bonds
            12.2.5  Private Bonds
12.3     PAYMENT BOND CLAIM PRACTICE
            12.3.1  Coverage of Bonds
            12.3.2  Notice Requirements
            12.3.3  Action on Bond
                        12.3.3.1   Federal Contracts
                        12.3.3.2   State Public Works Contracts
                        12.3.3.3   Private Contracts
12.4     PERFORMANCE BOND PRACTICE
            12.4.1  Contract Termination
            12.4.2  Notice Requirements
            12.4.3  Action on Bond
12.5     BAD FAITH 
 
CHAPTER THIRTEEN:  Liens

13.1   INTRODUCTION
13.2   NATURE OF LIEN
13.3   CREATION OF LIEN
13.4   PROPERTY SUBJECT TO LIEN
13.5   FULL PRICE LIEN VERSUS UNPAID BALANCE LIEN
13.6   PRIORITY OF LIEN
13.7   PERFECTING AND ENFORCING MECHANIC’S LIEN
13.7.1    Notice to Owner

13.7.2    Verified Statement of Lien

13.7.3    Lawsuit to Enforce Mechanic’s Lien

13.8   BONDING OFF LIEN
13.8.1    Bonding Off Lien if No Lawsuit Pending

13.8.2    Bonding Off Lien if Lawsuit Pending

13.8.3    Depositing Funds in Court’s Registry

13.9   LIEN RELEASES AND WAIVERS
13.9.1    Release of Recorded Lien

13.9.2    Waiver of Right to Claim Lien



CHAPTER FOURTEEN:  Effective Collection Techniques

14.1   INTRODUCTION
14.2   ESTABLISHING THE RELATIONSHIP
14.2.1    Proper Documentation

14.2.2    References

14.3   MONITORING THE RELATIONSHIP
14.4   ENFORCING RIGHT TO PAYMENT
14.4.1    Initial Due Diligence

14.4.2    Informal Resolutions and Workouts

14.4.2.1    Document all Agreements

14.4.2.2    Important Terms in Workout Agreements

14.4.3    Filing a Lawsuit

14.4.3.1    Whom to Sue

14.4.3.2    Where to File

14.4.3.2.1    Which County

14.4.3.2.2    Which Court

14.4.3.2.3    Common Causes of Action

14.4.4    Arbitration

14.5   ENFORCING A JUDGMENT
14.5.1    Locating Assets

14.5.2    Recording Judgment

14.5.3    Garnishments

14.5.4    Execution

14.6   RECOVERY ACTIONS
14.6.1    Fraudulent Transfers

14.6.2    Successor Liability

14.6.3    Piercing the Corporate Veil



CHAPTER FIFTEEN:  Dispute Resolution

15.1   DISPUTE RESOLUTION
15.1.1    Mediation

15.2   LITIGATION, ARBITRATION OR OTHER ALTERNATIVE METHODS OF DISPUTE RESOLUTION
15.2.1    Litigation

15.2.2    Arbitration



CHAPTER SIXTEEN:  Bankruptcy

16.1   INTRODUCTION TO BANKRUPTCY LAW AND PRACTICE
16.1.1    Types of Bankruptcy Cases

16.2   COMMENCEMENT OF CASE
16.2.1    Automatic Stay

16.2.1.1    General

16.2.1.2    Extent and Duration of Automatic Stay

16.2.2    Relief from Stay

16.2.3    Violation of Automatic Stay

16.2.4    Particular Examples/Exceptions

16.3   INITIAL CONSIDERATIONS UPON LEARNING OF A BANKRUPTCY FILING
16.3.1    Deadline to File Claim

16.3.2    Deadline to Object to Discharge

16.3.3    Reclamation Rights

16.4   THE CLAIMS PROCESS
16.4.1    DeTypes and Priority of Claims

16.5   FILING A CLAIM
16.5.1    Proof of Claim

16.5.2    Time to File

16.5.3    Claim Objections

16.5.4    Late Filed Claims

16.5.5    False Claims

16.5.6    Payment of Claims

16.6   ESTATE PROPERTY IN BANKRUPTCY
16.6.1    Use, Sale, or Lease of Estate Property

16.6.2    Executory Contracts and Unexpired Leases




 

TOP