ALABAMA

 

About the Author  |  This Book's Table of Contents  |  Order this Book  |  Seminars  |  Sponsors  |  Return to Map

ALABAMA CONSTRUCTION LAW
TABLE OF CONTENTS
 

CHAPTER ONE:  INTRODUCTION TO CONSTRUCTION LAW
1.1          DEFINITIONS 
1.2          SOURCES OF LAW
              1.2.1    Federal Procurement Law
              1.2.2    Alabama Statutes and Regulations
              1.2.3    Sales Law
              1.2.4    Common Law

CHAPTER TWO:  PROJECT DELIVERY SYSTEMS
2.1       CONVENTIONAL - DESIGN/BID/BUILD
2.2       DESIGN-BUILD
            2.2.1    Legality of Design-Build
            2.2.2    Obstacles to Design-Build
            2.2.3    Forms of Design-Build
2.3       CONSTRUCTION MANAGEMENT
            2.3.1    Agency CM
            2.3.2    CM At Risk
2.4       SOURCES OF CONTRACT DOCUMENTS

CHAPTER THREE:  PUBLIC CONSTRUCTION
3.1       INTRODUCTION
3.2       FEDERAL GOVERNMENT CONTRACTING
3.3       STATE AND LOCAL CONTRACTING
            3.3.1    Competitive Bidding
                        3.3.1.1    Bid Solicitation and Pre qualification
                        3.3.1.2    Bid Selection
                        3.3.1.3    Bid Bonds
            3.3.2    Enforceability of Bids
                        3.3.2.1    Contractor Bids
                        3.3.2.2    Bid Errors
                        3.3.2.3    Subcontractor and Supplier Quotations
            3.3.3    Post-Award Relief
3.4       BID PROTESTS
3.5       CONTRACT AWARD
3.6       PERFORMANCE OF PUBLIC WORKS CONTRACTS
            3.6.1    Contract Documents
            3.6.2    Payment Issues
            3.6.3    Change Orders
            3.6.4    Disputes
 
CHAPTER FOUR:  BUILDING CODES, STANDARDS AND PERMITS
4.1        INTRODUCTION
4.2        PURPOSE OF REGULATION OF CONSTRUCTION PRACTICE
4.3        MANDATORY CODES
              4.3.1 State
              4.3.2 Local Authorities.
4.4        BUILDING PERMITS
              4.4.1   Building Inspection
              4.4.2  Certificates of Occupancy
4.5       PENALTIES FOR VIOLATIONS

CHAPTER FIVE:  THE ARCHITECT/ENGINEER
5.1       INTRODUCTION
5.2       STATE LAWS GOVERNING THE PRACTICE OF ARCHITECTURE & ENGINEERING
            5.2.1    Statutory Regulation of Architects
            5.2.2    Statutory Regulation of Engineers
            5.2.3    Associations of Architects and/or Engineers
5.3       OWNER-ARCHITECT/ENGINEER AGREEMENT
            5.3.1    Types of Agreements
            5.3.2    Limitation on Services
            5.3.3    Additional Services
5.4       ARCHITECT-CONSULTANT AGREEMENTS
5.5       THE ARCHITECT/ENGINEER’S RESPONSIBILITIES
            5.5.1    Design
            5.5.2    Bidding and Negotiation
            5.5.3    Construction Administration
                        5.5.3.1    “Inspection”
                        5.5.3.2    Review of Applications for Payment
                        5.5.3.3    Review and Approval of Contractor Submittals
                        5.5.3.4    Authority to Order Changes
                        5.5.3.5    The Architect as Judge
            5.5.4    Post-Construction
5.6       THE ARCHITECT/ENGINEER’S LIABILITY7
            5.6.1    Liability to the Owner
            5.6.2    Liability to the Contractor1
                        5.6.2.1    Inadequate Plans and Specifications
                        5.6.2.2    Negligent Construction Administration
            5.6.3    Liability to Subcontractors
            5.6.4    Liability to Other Third Parties
5.7       PROFESSIONAL LIABILITY INSURANCE

CHAPTER SIX:  THE OWNER
6.1       INTRODUCTION
6.2       OWNER’S TYPICAL CONTRACT OBLIGATIONS
            6.2.1    Duty of Payment
            6.2.2    Duties of Cooperation and Disclosure
6.3       OWNER’S IMPLIED OBLIGATIONS
            6.3.1    Warranty of Plans and Specifications
            6.3.2    Duty Not to Delay, Hinder or Interfere With the Contractor’s Performance
6.4       OWNER’S MATERIAL CHANGE IN THE CONTRACT
6.5       DISCLAIMER OR WAIVER OF OWNER’S OBLIGATIONS

CHAPTER SEVEN:  THE CONTRACTOR
7.1       INTRODUCTION
7.2       QUALIFYING TO PERFORM CONSTRUCTION
            SERVICES
            7.2.1    General Contractor Licensing
            7.2.2    Foreign Corporation Qualification
            7.2.3    Exemptions
            7.2.4    Penalties for Noncompliance
7.3       PREFERENCE FOR RESIDENT CONTRACTORS AND LABOR  
7.4       BIDDING OR NEGOTIATIONS
7.5       STANDARD FORM CONTRACTS
7.6       THE TYPICAL CONSTRUCTION CONTRACT
            7.6.1    Integration Clause
            7.6.2    Site Visit
            7.6.3    Order of Precedence Clause.
            7.6.4    Permits and Fees
            7.6.5    Design Delegation7
            7.6.6    Review of Contract Documents and Field Conditions by Contractor 
            7.6.7    Compliance with Codes and Ordinances
            7.6.8    Contractor's Construction Schedule
            7.6.9    Shop Drawings, Product Data and Samples0
            7.6.10  Aesthetic Determination
            7.6.11  Claims and Disputes
            7.6.12  Differing Site Conditions
            7.6.13  Changes in the Work
            7.6.14  Time 
            7.6.15  Payment
                        7.6.15.1   Schedule of Values
                        7.6.15.2   Progress Payments
                        7.6.15.3   Retainage
                        7.6.15.4   Substantial Completion and Punchlists
                        7.6.15.5   Final Payment
            7.6.16  Insurance
                        7.6.16.1   Property Insurance
                        7.6.16.2   Liability Insurance
                        7.6.16.3   Loss of Use Insurance
            7.6.17  Statute of Limitations
            7.6.18  Termination7
                        7.6.18.1   Termination by Contractor
                        7.6.18.2   Termination by Owner
                        7.6.18.3    Contractor’s Warranty
            7.6.19  Attorneys’ Fees and Interest
7.7       RISK SHIFTING CLAUSES
            7.7.1    Indemnification
            7.7.2    Waiver of Subrogation
            7.7.3    Additional Insured Coverage
7.8       CONSTRUCTION DEFECTS CLAIMS

CHAPTER EIGHT:  THE SUBCONTRACTOR
8.1       INTRODUCTION
8.2       QUALIFYING TO PERFORM AS A SUBCONTRACTOR
            8.2.1    Subcontractor Licensing
            8.2.2    Nonresident Corporation Qualification
8.3       BIDDING OR NEGOTIATIONS
8.4       TYPICAL SUBCONTRACT PROVISIONS
            8.4.1    Scope of Work
            8.4.2    Time
            8.4.3    Payment
            8.4.4    Contractor's Warranty of Plans and Specifications
            8.4.5    Contractor's Duty Not to Hinder, Delay or Interfere
            8.4.6    Assignment of Subcontract
            8.4.7    Arbitration
            8.4.8    Subcontractor Claims and Disputes
            8.4.9    Subcontract Changes
            8.4.10  Indemnity Clauses.
            8.4.11  Insurance
            8.4.12  Subcontractor's Liability to Contractor
            8.4.13  Termination
            8.4.14  Attorney’s Fees and Interest
8.5       FLOW DOWN OF CONTRACT CLAUSES

CHAPTER NINE:  CHANGES IN THE WORK
9.1       INTRODUCTION
9.2       CHANGES – FORMAL OR CONSTRUCTIVE
9.3       FORMAL CHANGES – HOW DO THEY WORK?
            9.3.1    The Federal Changes Clause
            9.3.2    Agreed Changes
            9.3.3    Construction Change Directive or Interim Directed Change
            9.3.4    Minor Changes
            9.3.5    Pricing of Changes
9.4       WHO HAS AUTHORITY TO ORDER A CHANGE?
9.5       ORAL DIRECTIVES
9.6       CONSTRUCTIVE CHANGE
9.7       NOTICE OF CONSTRUCTIVE CHANGE
9.8       CARDINAL CHANGE
9.9       DEDUCTIVE CHANGES

CHAPTER TEN:  SITE CONDITIONS
10.1     INTRODUCTION
10.2     A CONTRACTOR’S RIGHT TO RELY ON THE OWNER’S REPRESENTATION OF CONDITIONS 
            10.2.1  Duty to Investigate Site
            10.2.2  Duty to Disclose
            10.2.3  Disclaimers
10.3     NOTICE    
10.4     CONTRACTUAL REMEDIES
            10.4.1  Type I Conditions
            10.4.2  Type II Conditions
            10.4.3  Hazardous Materials
10.5     SITE CONDITIONS NOT COVERED BY THE “DIFFERING SITE CONDITIONS” CLAUSE 
10.6     COMPENSATION

CHAPTER ELEVEN:  DAMAGES AND DELAYS
11.1     INTRODUCTION
11.2     DELAY AND ITS CONSEQUENCES
            11.2.1  Classification of Delays
                       11.2.1.1   Excusable Delay
                       11.2.1.2   Compensable Delay
                       11.2.1.3   Inexcusable Delay
                       11.2.1.4   Concurrent Delay
                       11.2.1.5   Critical Delay
            11.2.2  Consequences of Delay
11.3     CONTRACTUAL DELAY AND SCHEDULING
            PROVISIONS
11.4     REMEDIES FOR DELAYS
            11.4.1  Owner Remedies
            11.4.2  Contractor Remedies
11.5     PROOF AND RECOVERY OF DAMAGES FOR DELAY
11.5.1  Methods of measuring and Proving Delays
11.5.2  Types of Delay Damages
            11.5.2.1   Classification of Damages
            11.5.2.2   Contractors’ Delay Damages
            11.5.2.3   Owners’ Delay Damages
            11.5.2.4   Pricing and Proof of Damages
11.6     OTHER DAMAGES
            11.6.1  Owners’ Damages for Contractors’ Defective or Incomplete Performance
                        11.6.1.1   Types of Damages
                        11.6.1.2   Measure of Damages
            11.6.2  Contractors’ Damages
                        11.6.2.1   Types of Damages
                        11.6.2.2   Late Payment Damages
                        11.6.2.3   Termination Damages
11.7     ATTORNEYS’ FEES
11.8     PREJUDGMENT INTEREST
11.9     PUNITIVE DAMAGES
11.10   EXCLUSIONS OR LIMITATIONS OF DAMAGES
            11.10.1   “No Damages for Delay” Clauses
            11.10.2   Monetary Limitations
            11.10.3   Waivers of Consequential and Other Damages
            11.10.4   Duty to Mitigate Damages

CHAPTER TWELVE:  BONDS
12.1     INTRODUCTION
12.2     CONTRACTOR BONDS
            12.2.1  Federal Projects – The Miller Act
            12.2.2  State Public Works – The “Little Miller Act”
            12.2.3  Performance Bonds
            12.2.4  Payment, or Labor and Materials, Bonds
            12.2.5  Private Bonds
12.3     PAYMENT BOND CLAIM PRACTICE
            12.3.1  Coverage of Bonds
            12.3.2  Notice Requirements
            12.3.3  Action on Bond
                        12.3.3.1   Federal Contracts
                        12.3.3.2   State Public Works Contracts
                        12.3.3.3   Private Contracts
12.4     PERFORMANCE BOND PRACTICE
            12.4.1  Contract Termination
            12.4.2  Notice Requirements
            12.4.3  Action on Bond
12.5     BAD FAITH 
 
CHAPTER THIRTEEN:  LIENS
13.1     INTRODUCTION
13.2     ENTITLEMENT TO LIEN
13.3     TYPES OF LIENS
            13.3.1  Full-Price Lien
            13.3.2  Unpaid Balance Lien
13.4     PRIORITY OF LIENS
13.5     WAIVERS OF LIENS
13.6     ENFORCEMENT OF LIENS
            13.6.1  Notice to Owner
            13.6.2  Verified Statement
            13.6.3  Suit to Foreclose
                        13.6.3.1   Parties
                        13.6.3.2   Venue
                        13.6.3.3   Limitation of Actions
13.7     WRONGFUL FILING
 
CHAPTER FOURTEEN:  EFFECTIVE COLLECTION TECHNIQUES
14.1     INTRODUCTION
14.2     ADVANCE PROTECTION OF RIGHTS
14.3     DUE DILIGENCE DURING CONSTRUCTION
14.4     REMEDIES IN EVENT OF IMPASSE
            14.4.1  Suspension of Work
            14.4.2  Termination of Performance
14.5     BANKRUPTCY
14.6     COLLECTION ACTIONS
 
CHAPTER FIFTEEN:  DISPUTE RESOLUTION
15.1     INTRODUCTION
15.2     LITIGATION 
            15.2.1  Statutes of Limitations and Repose
            15.2.2  Pleadings
            15.2.3  Discovery
            15.2.4  Trial   
            15.2.5  Appeals
15.3     ARBITRATION
            15.3.1  The Arbitration Agreement
            15.3.2  Enforceability in Alabama
            15.3.3  Methods of Arbitration
            15.3.4  Effect of Arbitration On Ongoing Project and On Other Remedies
15.4     OTHER ALTERNATIVE DISPUTES RESOLUTION METHODS
            15.4.1  Mediation
            15.4.2  Mini-Trials and Non-Binding Arbitration
15.5     CONSIDERATIONS IN SELECTING REMEDY

 

TOP