ØMonthly
schedule review sessions.
qInsist
on quality updates –actual progress and realistic to-go plan.
qDon’t
let the schedule become a burden. Bigger not always better.
qReview
delays, current critical path, need for extensions or recovery plans.
§Require
critical path reports to show driving activities.
§Require
plots showing critical path(s) only.
qBeware
of downstream resequencing of activities.
qIs
the job really on schedule??? Or that
far ahead/behind?
qIssue
Minutes of Meeting.
Ø