Contractual Issues
ØThe contract establishes whether a claim can be pursued.
ØOwner subject to Adjustment of Completion Date  - Issue extensions if justified.
ØContractor subject to Responsibility for Completion - Get Back on Schedule!!!
ØConflict between these competing clauses often leads to claims.  
qWhat date are we trying to meet?  Who has delayed the project?
qTime extension - Owner grants relief to Contractor.
qSchedule recovery directive - Contractor recovers delay at its own expense.
qAcceleration directive - Owner compensates Contractor to recover delays.
qWhat if delays and responsibility are intertwined? Who pays for what?
§That’s why a good schedule is needed.