Categories of Delays
ØNot all delays provide entitlement.
ØExcusable/Compensable
qDelays beyond the Contractor’s control
qContractor entitled to a time extension and delay damages (O/H).
ØExcusable/Non-compensable
qDelays for which neither party at fault
qContractor entitled to time extension (i.e., LDs waived), but NOT delay damages.