Acceleration Claim
Required Linkage Between Event and Extra Cost
#1 Contractor Must Encounter
Delay Beyond its Control
#2 Contractor Must Submit
Proper Time Extension
Request to Justify Delay
#3 Owner Must Wrongfully
Deny Time Extension
Request
#5 Contractor Must Incur
Additional Cost
#4 Contractor Must
Accelerate to Overcome
Owner-Caused Delay