ØThe odd thing is that no one, including the expert, will ever be able to go back to the original Baseline CPM Schedule and correct the logic problems that led to the claim.
Ø
ØThe argument now will be whose expert do you believe?
Ø
ØThe right approach could have eliminated the claim.
ØThe right approach would have been to invest the time            during the approval process to review and discuss the baseline logic.
ØThe Owner and the Contractor must not miss the opportunity to reach an agreement on scheduling early on before the problems occur.