46
ØThe project NTP was issued January 2, 2004 as planned.
ØThe Contractor updated the baseline schedule at the end of the first month.
ØBoth of our previous schedule examples have been updated with identical progress and dates.
ØThe results are far from identical.
Ø
ØThe following Update No. 1 Bar Charts show the different results that came from the identical data: