ØBaseline CPM Schedule No. 1 Activity No. 210 Pour Cellar Slab On Grade finish date was extended from 4/2/04 to 4/6/04.
ØBaseline CPM Schedule No. 2 Activity No. 210 Pour Cellar Slab On Grade finish date is on time for 4/14/04.
ØThe Contractor with the faulty baseline schedule is claiming a critical path delay of four (4) calendar days.
ØThe delay claim entitlement is based on the Owner’s failure to obtain the building permit in a timely manner.
ØThe failure to obtain the permit delayed the project critical path Activities  #40 Erosion & Sediment Controls, #30 Miscellaneous Demolition, #50 Clear & Grub Lot, #55 Excavate Top Four Feet and #60 Install H Piles.