ØBaseline CPM Schedule No. 1 Activity No. 210 Pour
Cellar Slab On Grade finish date was extended from 4/2/04 to
4/6/04.
ØBaseline CPM Schedule No. 2 Activity No. 210 Pour
Cellar Slab On Grade finish date is on time for 4/14/04.
ØThe Contractor with the faulty baseline schedule is
claiming a critical path delay of four (4) calendar
days.
ØThe delay claim entitlement is based on the Owner’s
failure to obtain the building permit in a timely manner.
ØThe failure to obtain the permit delayed the project
critical path Activities
#40 Erosion & Sediment Controls, #30 Miscellaneous Demolition,
#50 Clear & Grub Lot, #55 Excavate Top Four Feet and #60 Install
H Piles.