Baseline No. 2 Schedule Report:
Page 2
Open Ends:
Ø
CPM requires one starting point and one ending
point.
Ø
The first activity will not have a predecessor.
Ø
The last activity will not have a successor.
Ø
Baseline CPM Schedule No. 2 meets CPM
specifications.