ØBaseline No. 1 Schedule Report:  Page 2
Open Ends:
ØCPM requires one starting point and one ending point.
ØThe first activity will not have a predecessor.
ØThe last activity will not have a successor.
ØThe CPM Schedule with 6 open end activities is flawed.