ØWe are now going to review two CPM Schedules for the same project.
ØThe project is in downtown Washington, D.C.
ØThe site footprint is very small and there are adjoining building issues.
ØIt is a five story structure.
ØWe are going to look at the foundation portion of the schedule which has 22 activities.  Overall, the schedule has 422 activities.
ØThe Contractor has one year to complete construction.