16
ØThe starting point for the solution is in the approval of the Project Baseline CPM Schedule.
Ø
ØYou cannot analyze a delay claim or prevent a delay claim if your project has a faulty Baseline CPM Schedule.
Ø
ØIt has been my experience that a very high percentage of Project Baseline Schedules are deficient and should not be used as the basis for delay claims.