17
ØThe most important first step is to start using logic diagrams as the primary means for approving the Project Baseline CPM Schedule.
Ø
ØWhen you base your approval on a bar chart, you have no idea as to the basis of the logic.
Ø
ØA bar chart does not communicate the construction logic and planning.  Only the developer of the bar chart knows the basis of the bar chart schedule planning .
How do you avoid a faulty project baseline schedule?