ØOkay, so where do we go from here?
Ø
ØRegardless of your positions regarding the debate, there is one outstanding predominate fact about CPM:
Ø
«CPM is a logic based network analysis system!  The dates for an activity early start, late start, early finish and late finish are calculated by a forward and backward pass through the network logic by the computer.