Ø
Ø
ØOkay, so where do
we go from here?
Ø
ØRegardless of your positions regarding
the debate, there is one outstanding predominate fact about
CPM:
Ø
«CPM is a logic based
network analysis system! The dates for an activity early start, late start, early
finish and late finish are
calculated by a forward and backward
pass through the network logic by the computer.